State significant project

Central-West Orana REZ Transmission

Every word above is the department's own, read from its Planning Portal page.

Stage: Determination
Case
SSI-48323210
Council
Warrumbungle Shire, Mid-Western Regional, Dubbo Regional, Upper Hunter Shire
Address
Linear Transmission Infrastructure Commencing At Wollar Substation
Type
State Significant Infrastructure
Kind of development
Electricity supply
What it is
Development of new twin double circuit 500 kV transmission lines between Wollar and the proposed substations at Merotherie and Elong Elong, and connections from these lines to renewable energy generation and storage projects in the CWO REZ
Decision
Approved
Decided by
Minister
Determined
26 June 2024