Stage: Determination
- Case
- SSD-63235720
- Council
- City of Ryde
- Address
- 1-5 Khartoum Road, Macquarie Park
- Type
- State Significant Development
- Kind of development
- Data Storage
- What it is
- Construction and operation of a 5 storey data centre with a building height of 45 m and a capacity of 35 MW, diesel storage, part road construction, landscaping, carparking and associated infrastructure.
- Decision
- Approved
- Decided by
- Director
- Determined
- 11 March 2026